Round Base/Flasher®

STEP 1:  Cut to pipe diameter marked on Flasher® (this is approximately 20% smaller than the diameter of the pipe).
STEP 2:  Slide the Flasher® down the pipe, using water to lubricate if necessary.
STEP 3:  Form & bend the aluminum base of the Flasher® to fit the surface of the roof.
STEP 4:  Seal the Flasher® by applying urethane or silicone sealant between the flashing & the roof.  Use a large slot screwdriver to press the base 
down tightly.
STEP 5:  Fasten the Flasher® with weather-resistant fasteners to complete the seal.


Square Base Flashing/Masterflash®

STEP 1:  Trim opening to 20% smaller than pipe diameter.
STEP 2:  Slide down over pipe.
STEP 3:  Apply urethane or silicone sealant between the Masterflash® and roof.
STEP 4:  Press down, bending the flashing to fit irregularities.  Use a large slot screwdriver to press into tight angles.
STEP 5:  Use fasteners to finish sealing.
 


 Round Base Retrofit Flashing/Retrofit Dektite®

STEP 1:  Begin cutting opposite of the mechanical locking joiner.  Cut through the joiner with tin snips.
STEP 2:  Wrap the flashing around the pipe.  Engage the top section of the joiner first, then proceed down until the joner is completely engaged.
STEP 3:  Crimp joiner tightley, starting at the top by squeezing joiner "fingers" with pliers.
STEP 4:  Apply sealant to the underside of the ribbed aluminum base.  Press Retrofit Dektite against contours of the penl configuration.
STEP 5:  Attach the Retrofit Dektite® to the panel with self-drilling screws.  Screws should be spaced as necessary to avoid gaps between the base and the panel.
STEP 6:  Apply additional sealant around the top of the flashing and along the mechanical locking joiner seam.
 


Square Base Retrofit Flashing/Retrofit Masterflash®

STEP 1:  Choose appropriate size Retrofit Masterflash®.  If necessary trip opening to be about 20% smaller than the pipe diameter.
STEP 2:  Wrap the flashing around the pipe and install all snap rivets to seal the flange.
STEP 3:  Press the Retrofit Masterflash® down, bending it to conform to the roof profile and/or roof irregularities.  A blunt tool will help press the flashing into tight roof angles.
STEP 4:  Apply silicone or urethane sealant between the base of the flashing and the roof.
STEP 5:  Use fasteners to complete the sealing.  For UPC installation, fastener spacing shall not exceed 1 ½".
STEP 6:  Install supplied cable tie at the upper-most part of the flashing and apply sealant to any gaps.




 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

   